How to choose a builder for a renovation or extension
A renovation is the largest cheque most households write to a single tradesperson. Regulators know it, which is why building has its own licences, contracts, deposit caps, insurance and cooling-off rules on top of the general consumer law.
Licence thresholds
| State | When a licensed or registered builder is required | Regulator |
|---|---|---|
| NSW | Residential building work over A$5,000 in labour and materials, including GST | Building Commission NSW |
| Victoria | Work worth more than A$10,000. Also any work needing a building permit, such as restumping | Building and Plumbing Commission |
| Queensland | Building work valued over A$3,300 | QBCC |
| WA | Most work of A$20,000 or more that requires a building permit | Building and Energy |
| SA | Anyone doing building work for others needs a building work contractor's licence. The state's licence page gives no dollar threshold | Consumer and Business Services |
Sources: NSW, Victoria, Queensland, WA, SA.
NSW adds a detail that catches people out: its pool building guidance says the name on the contract must be exactly the same as the name on the licence. Check that before you sign with "Dave's Building Group" when the licence belongs to David personally.
Contracts and cooling-off
NSW. A written contract is compulsory over A$5,000. Jobs from A$5,000 to A$20,000 get a "small jobs" contract. Over A$20,000 the contract must include a progress payment schedule, a termination clause, a 17-item checklist and a cooling-off period of five clear business days.
Victoria. A major domestic building contract is required for work over A$10,000.
Queensland. The QBCC's pool guidance says work over A$3,300 requires a contract and comes with a 5 business day cooling-off period.
WA. Fixed-price contracts from A$7,500 to A$500,000 fall under the Home Building Contracts Act 1991.
Deposits
The caps are in our deposits piece. In short: 10% in NSW, 10% or 5% in Victoria and Queensland depending on the contract price, and 6.5% in WA.
Insurance against the builder going bust
| State | Cover required when | What the regulator says |
|---|---|---|
| NSW | Work over A$20,000 | It is illegal to ask for a deposit or other payment until cover is in place and the certificate has been given to you |
| Victoria | Work over A$20,000 from 1 July 2026 (A$16,000 before that) | The practitioner must provide a certificate of currency before taking a deposit or starting work |
| WA | Permit work over A$20,000 | Covers lost deposits up to A$40,000 and incomplete or defective work up to A$200,000 |
No certificate, no deposit. That one rule would have saved a great many people.
Before you choose
NSW's step by step guide suggests asking past clients three things: did the job finish on time and on budget, were defects fixed promptly, and what else is the builder working on now. The last one tells you whether your job will get a supervisor or a weekly drive-by.
Paying as the job goes
Progress payments should match work completed. Consumer Affairs Victoria says to check, before each payment, that the stage is complete, meets the contract and has passed the building surveyor's inspection. The QBCC warns that with cost-plus contracts, reports show final costs can exceed expectations by 50 to 100 per cent.
After handover
NSW gives statutory warranties on residential building work: 6 years for major defects and 2 years for all other defects, for contracts signed on or after 1 February 2012, per its dispute guidance. Other states have their own periods; ask your regulator.
Quick questions
The builder wants 30% up front for materials. Is that legal?
Not on a regulated home building contract in NSW, Victoria, Queensland or WA, where the caps range from 5% to 10% (20% in limited off-site cases). Overpaying can also put your insurance cover at risk.
Do I need a licensed builder for a A$4,000 deck?
It depends on the state: that is over Queensland's A$3,300 threshold and under NSW's A$5,000 one. A deck may also need a permit, which changes the answer. Ask your regulator.
Sources
Opened and read in November 2026. Follow the links for the current wording.
- Contracts for residential building work NSW Government
- Step by step guide to choosing the right tradesperson or builder NSW Government
- Categories and classes of building and trade work NSW Government
- Resolving building disputes with your builder or tradesperson NSW Government
- About builders, tradespeople and other building practitioners Consumer Affairs Victoria
- Deposits and payments for building work Consumer Affairs Victoria
- When you need a licence Queensland Building and Construction Commission
- Understanding deposits and progress payments Queensland Building and Construction Commission
- Building or renovating your home WA Building and Energy
- Building work contractor's licence SA.GOV.AU
General information for Australian consumers, not legal advice. Spotted an error? Tell us.