The tradie has vanished mid-job. Do these things in this order

The scaffolding is still up, the bathroom is a concrete shell, and the phone goes to voicemail. It is maddening, and what you do in the next fortnight decides how much of your money you see again.

Step 1: Record everything, today

Photograph and video the whole site: finished work, unfinished work, materials left behind, tools. Add something showing the date. List what has been done against the quote, and what you have paid.

This is your evidence of the state they left it in. Once another tradie touches it, it is gone.

Step 2: Make it safe, and only that

If there is live wiring, an open roof or a gas smell, get a licensed tradesperson to make it safe immediately and keep the invoice. Limiting the damage is expected of you. Finishing the job is not yet.

Step 3: Check you have the right person

Look up the ABN and any licence. Has the licence been suspended? Is the ABN cancelled? Search the business name with the word "liquidation". If the business has gone under, skip ahead: you are now dealing with an insurer or a liquidator, and for home building work your state's building insurance scheme may apply. In NSW you must notify the Home Building Compensation Fund insurer in writing as soon as you become aware of defective or incomplete work.

Step 4: Send a written deadline

One message, by email and text, with no venting in it:

  • what is unfinished,
  • a date to return to site (seven days is fair for most jobs) and a date to finish,
  • a statement that if they do not, you will treat the contract as ended, have the work completed by someone else and claim the extra cost.

There is a template on our letters page. This step matters legally. A service must be supplied within a reasonable time, and the deadline is what turns a vague delay into a clear failure.

Step 5: Stop paying

Do not pay another instalment for work not done. If you prepaid by card and the business is not responding, ask your bank about a chargeback now, because the time limits are short: 45 to 120 days from the transaction, according to Consumer Affairs Victoria.

Step 6: End it properly

If the deadline passes, send a short second message: the deadline has passed, you are terminating the contract because the services were not supplied within a reasonable time, and you will be seeking a refund of amounts paid for work not done plus the additional cost of completion.

Under the consumer law, a failure that cannot be fixed within a reasonable time is a major failure, which is what gives you the right to cancel.

Step 7: Get the completion quotes

Get two written quotes to finish the job to the original specification. Ask each tradie to separate "finishing what was left" from "fixing what was done badly". The difference between what the job should have cost and what it now costs in total is the core of your claim.

Step 8: Claim

Send a letter of demand with the figures. No response: your state's fair trading agency, the building regulator for building work, then the tribunal or court. Limits and fees are in our disputes section.

What not to do

  • Do not change the locks and say nothing. Say something, in writing.
  • Do not post accusations online while the claim is live. It gives the other side something to argue about.
  • Do not accept "I will be back Monday" for a fourth time without a date in writing.

Quick questions

The tradie says he stopped because I owe him money. Who is right?

Compare payments made against stages completed. If you have paid for more than has been done, the hold-up is his. If a stage payment really is overdue, pay it or explain in writing why you dispute it.

Can I claim for the delay itself?

You can claim losses that were a foreseeable result, such as extra rent or storage, with receipts. Keep them separate from the cost of completion.

Sources

Opened and read in November 2026. Follow the links for the current wording.

General information for Australian consumers, not legal advice. Spotted an error? Tell us.